Tender Details
Description / Scope of Work
IESCO invites bids for the construction of a 132 KV grid station at DHA Phase VII (Rose) under the cost deposit head. The estimated contract value is Rs. 162,445,456 including PST. This national-level procurement is for construction works to be executed in Islamabad, Federal Territory. The project involves establishing critical electrical infrastructure to support power supply distribution in the designated area. The bidding process follows a single-stage, one-envelope format, ensuring transparent and efficient procurement in compliance with national standards.
Bidders must meet specified eligibility criteria including relevant PEC (Pakistan Engineering Council) registration, experience in similar grid station construction projects, and financial capability to execute works of this scale. Bid security requirements and technical documentation standards are detailed in the tender document. Contractors must demonstrate past construction experience, adequate technical staff, appropriate equipment resources, and financial resources sufficient to complete the project within the specified timeframe.
Bid documents are available from IESCO-PMU at the Head Office, Street #40, Sector G-7/4, Islamabad. Bids must be submitted as per the closing date and time specified in the tender notice. The bid opening will be conducted as per procurement regulations. For further information, contact IESCO-PMU via phone +92-319-599-2205 or email iescopmu@iesco.com.pk. All bidders must comply with the General and Special Conditions of Contract and submit required forms including the Integrity Pact and Performance Guarantee.
For Bidders: Our Analysis PAKISTANTENDER INSIGHT
Independent analysis by PakistanTender — not part of the official notice. Always confirm details against the original tender document.
IESCO is procuring construction of a major 132 KV grid station in Islamabad valued at approximately Rs.
162.4 million. This is a substantial single-contract works award using standard national bidding procedures. The project requires demonstrated PEC experience in substation/transmission infrastructure, significant technical resources, and working capital. Timeline from bid closing (September 15, 2026) to execution will be tight. Contractors must carefully assess defect liability and performance guarantee obligations detailed in contract conditions.
Who can bid: Bidders typically require PEC registration in the relevant category for grid station and transmission infrastructure construction, valid NTN, and SECP registration if incorporated. Minimum turnover and experience completing similar-value projects typically required. The notice specifies detailed eligibility criteria at page 37; review for specific PEC grade, experience thresholds, and financial ratio requirements.