Sui Northern Gas Pipelines Limited invites bids for construction of two 12-inch diameter high-pressure natural gas pipelines using Horizontal Directional Drilling (HDD) technology to cross the CRBC Canal in District D.I Khan and Gambella Nullah in District Laki, Khyber Pakhtunkhwa. This is a non-consultancy services contract awarded through national competitive bidding using a single-stage two-envelope procurement process. The project scope encompasses complete pipeline installation through HDD methodology, including site preparation, drilling operations, pipe laying, testing, and commissioning of the crossings. The work is located in two districts of KPK province, involving specialized underground drilling techniques to minimize surface disruption while ensuring safe gas infrastructure development.
Bidders must demonstrate prior experience in HDD pipeline crossing projects of 12 inches diameter or larger completed within the last five years. Eligibility criteria require contractors to be registered with relevant Pakistani authorities and possess valid licenses for conducting high-pressure gas pipeline construction. A bid securing declaration is mandatory, with details specified in the bidding documents. Bidders must submit technical proposals demonstrating equipment capability, experienced personnel, and detailed methodology for executing both HDD crossings successfully.
Bid documents are available from Sui Northern Gas Pipelines Limited, Network Planning and Design Department, 3rd Floor, Gas House, 21-Kashmir Road, Lahore. Bids must be submitted in two envelopes containing technical and financial proposals. The contact person is Technical Officer Sajid Islam, reachable at +92-333-470-1002 or sajid.islam@sngpl.com.pk. Interested bidders should obtain complete tender documents to review specifications, scope of work, price schedules, general and special conditions of contract, and all required forms before preparing their proposals.
For Bidders: Our Analysis PAKISTANTENDER INSIGHT
Independent analysis by PakistanTender — not part of the official notice. Always confirm details against the original tender document.
SNGPL is tendering two HDD gas pipeline crossings (12-inch diameter) in remote KPK locations.
This is specialized work requiring proven HDD experience with 12"+ pipelines in the last five years; contractors without such portfolio will not qualify. The scope spans design, construction, testing and commissioning of underground crossings at two separate canal/nullah sites. Given the technical complexity and regulatory nature of gas infrastructure, only experienced contractors with appropriate licenses and equipment should bid. Timeline is tight (closing 14 October 2026); documentation and prior project evidence must be prepared in advance.
Who can bid: Bidders typically must hold PEC registration (category A or B for pipeline construction), valid gas utility contractor license, NTN with FBR, and SECP company registration. Prior demonstrated experience with HDD pipeline crossings of 12 inches or larger within five years is explicit. HSE compliance statement and integrity pact signature are required. No restrictions on nationality stated, but SNGPL vendor registration may be prerequisite.